How building plan sanction in Delhi works under the 2016 bye-laws
The Unified Building Bye-Laws for Delhi, 2016 (UBBL) replaced the 1983 bye-laws with a risk-based model: the smaller and simpler the building, the more the government relies on the registered architect. Since October 2019, plots up to 500 sq m have been sanctioned online on self-certification: the architect files, a rule engine checks the drawings, the fee is paid online and a digitally signed sanction letter is generated.
UBBL 2016 residential risk categories (Table 3.1) and decision clocks (clauses 3.1.0 and 3.1.1.2)
| Risk category |
Plot size |
Process |
Decision time |
| Very low |
Up to 105 sq m (about 125 sq yd) |
“SARAL” route: submission with documents and fees is itself the deemed sanction |
On submission |
| Low |
Above 105 up to 500 sq m (about 126–598 sq yd) |
Architect or engineer may issue the permit after filing; or the owner opts for sanction by the authority |
10 days if the authority sanctions |
| Moderate |
Above 500 sq m |
Sanctioned by the authority |
20 days |
| High |
Group housing; height 15 m and above |
Sanctioned by the authority |
30 days |
Three readings. First, a 200–400 sq yd plot is low risk; a plot of about 600 sq yd or more crosses 500 sq m and becomes moderate, with an authority decision and plinth inspection. Second, Table 3.1 describes these categories as “below 15 m, including stilt”, while stilt + 4 runs to 17.5 m; let your architect confirm how the file is routed rather than assuming a category. Third, self-certification puts the risk on the architect: in June 2023 the MCD was reported to have barred 140 architects for three years and revoked plans passed on wrong information. A cheap architect who “passes” a non-compliant plan saves you nothing.
The statutory clocks and deemed approval
The sanctioning authority must decide within the category time or 30 days, whichever is less (clause 2.3.1). Outside agencies must respond within 15 days or the category time, whichever is less, or their NOC is deemed issued (clause 2.3.3). If the authority misses its deadline, the plan is deemed sanctioned, released once the fees are deposited (clause 2.3.4). The same clause warns that a deemed sanction authorises nothing against the lease, the Master Plan or the bye-laws. Silence from the MCD is not permission to build a fifth floor.